Transportation EISComment open
NYSDOT ~ NEPA and SEQRA scoping
CNY Forward
Studies Route 31, Route 11, I-81 and Route 481 for traffic operations, truck routing, safety, bridges, walking, biking and transit.
Meetings Jul 30 and Aug 6Comments Aug 14Outreach office open
Official launch and dates ↗
Regional transportationPhase 2 begins
NYSDOT ~ I-81 Contract 6
I-81 live contract ledger
Track the program by awarded contract rather than one static total. Contract 6 begins Phase 2 with major highway, street and utility work.
$2.1B award25 local streetsWater and sewer replacement
Contract 6 award ↗
Customer service transmissionArticle VII review
PSC Case 24-T-0120
Micron 345 kV service laterals
National Grid proposes four underground laterals between the expanded Clay Substation and the four Micron fab areas. This is customer-specific infrastructure and is tracked separately from regional reliability work.
Four laterals0.95 to 2.07 milesClay Substation expansion
Case information ↗
Electric transmissionArticle VII review
PSC Case 25-T-0184
Black River to Clay rebuild
A regional reliability project ending at Clay Substation. The case record is regional in scope, so the ledger separates it from customer-specific interconnection work.
60.9 miles115 kVNew Staplin Creek substation
Case information ↗
Grid rules and cost allocationActive proceeding
PSC Case 26-E-0045
Large-load interconnection rules
The PSC is reviewing queue discipline, upgrade-cost allocation, tariff structure, reliability and transparency for data centers and other large electric loads.
11.9 GW queue in Feb 20268.3 GW added in 2025Comments extended to May 13, 2026Response comments due Jun 15, 2026
Notice extending comment deadlines ↗
Water withdrawalPermit issued
DEC 7-3512-00173/00001
OCWA Lake Ontario pump upgrades
Three larger pumps, motors and drives increase permitted raw-water capacity. Two parallel 42-inch mains connect OCWA's Eastern Branch to White Pine.
62.5 to 93.5 MGDThree replacement pumpsIssued Jun 8, 2026
Connected-action dashboard ↗
Potable water transmissionApplication complete
DEC 7-3124-00616/00002
White Pine parallel 42-inch water mains
OCWA proposes two parallel mains from the existing Eastern Branch service main to White Pine Commerce Park for Micron construction and initial operation.
Two mains42-inch diameterPotable water service
Application record ↗
Wastewater conveyanceUnder construction
Onondaga County WEP capital project
White Pine pump station & force mains
A new station and 20,400 feet of 10-inch and 18-inch force mains serve phased development near Route 31 and Caughdenoy Road.
$36.4MPeak 5.5 MGDThrough Oct 2026
County project page ↗
Treatment & reuseMixed status
SPDES NY0030317
Oak Orchard expansion
The discharge permit is final. Selected wetland, conveyance-corridor and mitigation approvals remain under review as the treatment and reuse systems advance.
10 to 30.8 MGDReuse outfalls 006 and 007SPDES issued Apr 10
Connected-action dashboard ↗
Energy & communicationsGas permit issued
DEC 7-3124-00603/00003
Gas and fiber utility corridors
The gas main and Route 31 fiber routing are distinct connected actions. Track easements, construction timing, outages, restoration and long-term operating data separately.
16,160 ft gas mainFiber in existing right of wayGas issued May 20
Gas-main project record ↗
Construction logisticsIn project buildout
Micron Final EIS ~ applicant analysis
Micron rail spur & conveyor
The rail system is designed to move aggregate to the campus and reduce long-duration truck demand. Results should be compared with actual rail and truck counts.
9M cubic yards aggregate1,500 short tons per hourAbout 7,300 trips per month avoided
Final EIS and appendices ↗
Adjacent developmentFinal scope
OCIDA ~ Generic EIS
White Pine Science & Technology Park
A separate 104-acre supplier and technology park may support manufacturing, research, warehousing, processing and data-management uses with additional utility demand.
104 acresFinal scope Jun 17Draft GEIS next
Final scope notice ↗
Regional design benchmarkSite plan review
Cayuga permits ~ Lake Hawkeye company filing
Cayuga / Lake Hawkeye benchmark
At the former Cayuga power site, current DEC permits reduce authorized withdrawal and discharge from about 245 to 1 MGD. Company filings separately list a potential data-center redevelopment still in site plan review.
About 245 to 1 MGD400 gross / 320 critical IT MW0 contracted in Q1 filing