salt to siliconCNY infrastructure data
Source library ~ verified July 29, 2026

Source records
and datasets.

Searchable primary documents, project filings and clearly attributed company records for Central New York infrastructure.

Source library.

Search titles, agencies, systems or evidence classes. The list favors permits, orders, dockets, official project pages and filings.

RecordCategoryEvidenceRecord dateLink
S01 ~ Town of Lysander official records

Town notices, committee agendas, revised community-benefit suggestions, water presentation and consultant RFP.

LocalVerified2026-07-23Open record ↗
S02 ~ Town of Lysander data-storage-center moratorium

Local Law No. 4 creates the six-month planning pause.

LocalVerified2026-05-07Open record ↗
S03 ~ New York Executive Order 62

50 MW threshold, state-permit abeyance, GEIS, local-permit exception and community-investment framework.

StateVerified2026-07-14Open record ↗
S04 ~ Responsible Data Center Development Act

Legislative record for S10642 and A11560.

StateVerified2026-06-04Open record ↗
S05 ~ PSC Case 26-E-0045 ~ large-load interconnection

Queue discipline, cost allocation, tariff structure, reliability and transparency.

GridVerified2026-02-12Open record ↗
S06 ~ NYSDEC Micron permit dashboard

Final EIS, campus permits and connected-action permit dates and status.

MicronVerified2026-07-29Open record ↗
S07 ~ Micron Final EIS and appendices

Project design, utilities, rail logistics, construction and environmental analysis.

MicronVerified2025-11-12Open record ↗
S08 ~ Micron first-concrete announcement

Company-reported July 9 construction milestone.

MicronCompany Reported2026-07-09Open record ↗
S09 ~ Micron 345 kV service laterals

PSC Case 24-T-0120, four underground laterals and Clay Substation expansion.

GridVerified2026-07-29Open record ↗
S10 ~ Black River to Clay rebuild

PSC Case 25-T-0184, 60.9-mile 115 kV regional transmission rebuild.

GridVerified2026-07-29Open record ↗
S11 ~ OCWA raw-water pump station

Permit record for increase from 62.5 to 93.5 MGD and three replacement pumps.

WaterVerified2026-06-08Open record ↗
S12 ~ White Pine parallel 42-inch water mains

Two parallel mains from the OCWA Eastern Branch to White Pine Commerce Park.

WaterVerified2026-07-29Open record ↗
S13 ~ White Pine pump station and force mains

County project cost, route, 20,400 feet of force mains and 5.5 MGD peak design.

WastewaterVerified2026-07-29Open record ↗
S14 ~ Oak Orchard final SPDES permit NY0030317

Phased flows, reuse outfalls, emerging-contaminant monitoring and action-level response.

WastewaterVerified2026-04-10Open record ↗
S15 ~ Micron and White Pine 16-inch gas main

16,160 feet of new steel main from Route 31 to the campus.

MicronVerified2026-07-29Open record ↗
S16 ~ White Pine Science & Technology Park

104-acre adjacent park, final scope and Draft GEIS next.

DevelopmentVerified2026-06-17Open record ↗
S17 ~ CNY Forward transportation EIS

Route 31, Route 11, I-81 and Route 481 scoping and public-comment dates.

TransportVerified2026-07-29Open record ↗
S18 ~ I-81 Contract 6

Phase 2 award, $2.1 billion, 25 local streets and utility replacement.

TransportVerified2026-07-03Open record ↗
S19 ~ Cayuga Operating final water permits

Final 2026 water-withdrawal and SPDES permits reduce authorized volumes from about 245 to 1 MGD.

DevelopmentVerified2026-04-13Open record ↗
S20 ~ TeraWulf Q1 2026 investor presentation

Company-reported Lake Hawkeye site-plan-review status, 400 gross MW and 320 critical IT MW, with no contracted capacity shown.

DevelopmentCompany Reported2026-05-11Open record ↗
S21 ~ Onondaga Lake Superfund reuse profile

EPA record on sediment removal, capping, habitat restoration and continued reuse.

ContextVerified2026-07-29Open record ↗
S22 ~ Harborview Aquarium project

County record on the under-construction aquarium and 33-foot main habitat.

ContextVerified2026-04-02Open record ↗

Evidence classifications.

Verified

Primary source record.

Permits, orders, dockets, public notices and official project pages receive this label.

Reported

Attributed statement.

The statement may be useful, but remains attributed until measured or independently confirmed.

Estimated

Estimated or calculated value.

Method, assumptions and source inputs should remain visible.

Unknown

Data not found in reviewed records.

Unknown is a result, not an invitation to guess.