salt to siliconCNY infrastructure data
Frozen public record ~ verified July 29, 2026

Regional infrastructure
research snapshot.

This page preserves the wording, evidence classes, project states and source links reviewed for version 2026.07.29. It will not change when later releases are published.

13 tracked entriesAppend-only archivePrimary sources linked

Project status at publication.

verified and reported

Town of Lysander data center planning

A six-month local moratorium is in effect. Town materials posted through July 23 include advisory committee agendas, revised community-benefit suggestions, a water presentation, Executive Order 62 materials and a consultant RFP. A project-specific environmental application was not located in the reviewed record.

Primary record ↗
verified

New York Executive Order 62

Incomplete discretionary DEC permits for qualifying data centers are held while a statewide Generic Environmental Impact Statement is developed. Local permits are not paused by the order.

Primary record ↗
verified and company reported

Micron semiconductor campus

The Final EIS is accepted, major environmental permits are issued and first concrete was poured on July 9, 2026.

Primary record ↗
verified

Oak Orchard wastewater treatment plant

The final SPDES permit authorizes phased treatment and reuse up to 30.8 MGD. PFOA and PFOS have 10 ng/L action levels with confirmatory sampling and minimization requirements; other listed PFAS are monitored.

Primary record ↗
verified

CNY Forward transportation EIS

Scoping meetings are scheduled for July 30 and August 6, 2026. Comments are due August 14, 2026.

Primary record ↗

Infrastructure watchlist at publication.

WorkSystemStatusKey metricEvidenceSource
CNY Forward transportation EIStransportcomment openRoute 31, Route 11, I-81 and Route 481verifiedOpen ↗
I-81 Contract 6transportawarded$2.1 billion, 25 local streets and water and sewer replacementverifiedOpen ↗
Micron 345 kV underground service lateralsgridarticle vii reviewFour laterals, 0.95 to 2.07 miles, plus Clay Substation expansionverifiedOpen ↗
Black River to Clay transmission rebuildgridarticle vii review60.9 miles at 115 kVverifiedOpen ↗
New York large-load interconnection and cost-allocation proceedinggridactive proceeding11.9 GW future large-load queue as of February 2026verifiedOpen ↗
OCWA Lake Ontario raw-water pump upgradeswaterpermit issued62.5 to 93.5 MGD permitted withdrawal capacityverifiedOpen ↗
OCWA White Pine parallel water mainswaterapplication completeTwo parallel 42-inch mains to White Pine Commerce ParkverifiedOpen ↗
White Pine pump station and force mainswastewaterconstruction20,400 feet, peak 5.5 MGDverifiedOpen ↗
Oak Orchard treatment and reuse expansionwastewatermixed10 to 30.8 MGD phased design flowverifiedOpen ↗
Micron and White Pine gas and fiber corridorsgridgas permit issued16,160-foot gas main plus Route 31 fiber routingverifiedOpen ↗
Micron rail spur and aggregate conveyortransportproject buildout9 million cubic yards aggregate and applicant estimate of 7,300 avoided truck trips per monthapplicant reported in final eisOpen ↗
White Pine Science & Technology Parkdevelopmentfinal scope104-acre business park, Draft GEIS nextverifiedOpen ↗
Cayuga Operating site and Lake Hawkeye regional benchmarkdevelopmentcurrent permits issued future site plan reviewCurrent water permits about 245 to 1 MGD; company pipeline 400 gross and 320 critical IT MWverified and company reportedOpen ↗