Town of Lysander data center planning
A six-month local moratorium is in effect and the advisory committee is active. A project-specific environmental application was not located in the reviewed record.
Primary record ↗This page preserves the wording, evidence classes, project states and source links reviewed for version 2026.07.27. It is not the live dashboard and will not change when later releases are published.
A six-month local moratorium is in effect and the advisory committee is active. A project-specific environmental application was not located in the reviewed record.
Primary record ↗Incomplete discretionary DEC permits for qualifying data centers are held while a statewide Generic Environmental Impact Statement is developed. Local permits are not paused by the order.
Primary record ↗The Final EIS is accepted, major environmental permits are issued and first concrete was poured on July 9, 2026.
Primary record ↗The final SPDES permit authorizes phased treatment and reuse up to 30.8 MGD. Selected connected-action permits remain under review.
Primary record ↗Scoping meetings are scheduled for July 30 and August 6, 2026. Comments are due August 14, 2026.
Primary record ↗| Work | System | Status | Key metric | Evidence | Source |
|---|---|---|---|---|---|
| CNY Forward transportation EIS | transport | comment open | Route 31, Route 11, I-81 and Route 481 | verified | Open ↗ |
| I-81 Contract 6 | transport | awarded | $2.1 billion, 25 local streets | verified | Open ↗ |
| Micron 345 kV underground service laterals | grid | article vii review | Four laterals, 0.95 to 2.07 miles, plus Clay Substation expansion | verified | Open ↗ |
| Black River to Clay transmission rebuild | grid | article vii review | 60.9 miles at 115 kV | verified | Open ↗ |
| New York large-load interconnection and cost-allocation proceeding | grid | active proceeding | 11.9 GW future large-load queue as of February 2026 | verified | Open ↗ |
| OCWA Lake Ontario raw-water pump upgrades | water | permit issued | 62.5 to 93.5 MGD | verified | Open ↗ |
| White Pine pump station and force mains | wastewater | construction | 20,400 feet, peak 5.5 MGD | verified | Open ↗ |
| Oak Orchard treatment and reuse expansion | wastewater | mixed | 10 to 30.8 MGD | verified | Open ↗ |
| Micron and White Pine gas and fiber corridors | grid | gas permit issued | 16,160-foot gas main plus Route 31 fiber routing | verified | Open ↗ |
| Micron rail spur and aggregate conveyor | transport | project buildout | 9 million cubic yards aggregate and applicant estimate of 7,300 avoided truck trips per month | applicant reported in final eis | Open ↗ |
| White Pine Science & Technology Park | development | final scope | 104-acre business park, Draft GEIS next | verified | Open ↗ |
| Cayuga Operating site and Lake Hawkeye regional benchmark | development | current permits issued future site plan review | Current water permits about 245 to 1 MGD; company pipeline 400 gross and 320 critical IT MW | verified and company reported | Open ↗ |